Itafós Phosphate Project

Itafόs – Current Operations

In October 2008, MBAC Fertilizer Corp. purchased 100% of the shares of Itafós Mineração Ltda, located in central Brazil, near the border of Goiás and Tocantins states. The Company presently operates this small-scale mine and processing facility which has a production capacity of approximately 100ktpa. The current operation processes rock phosphate which is sold to local farmers for direct application.

The Itafós Arraias SSP Project

MBAC is now focused on the development of a higher volume and much larger mining operation, which is expected to be in place by mid 2012. The Itafós Arraias SSP Project will include a new mine and mill facility, a sulphuric acid plant, an SSP plant and a granulation plant. At full capacity, the proposed beneficiation plant is expected to generate 330 ktpa of phosphate rock concentrate at 28% P2O5. This phosphate concentrate will be used to produce 500 ktpa of SSP. Beyond this proposed first phase of development, the Company is also actively investigating the potential for a second phase of development which could double production and potentially be in place as early as 2015.

Project Milestones Completed

43-101 Technical reports significantly increased resources at Itafόs

  • April: increased M&I resource base from 12.9 Mt to 28.3 Mt @ 4.3%
  • July: increased M&I resource base to 58.8 Mt @ 5.01%
  • Exceeded 2011 target of 45 Mt Proven and Probable

APRIL 2010: Report confirms robust project (AMEC)

  • Validation of production process → Itafós Arraias SSP Project is viable
  • Economic analysis with technical report capex and opex numbers confirm a robust project

SEPT 2010: Itafós Arraias SSP Project Positive Definitive Feasibility Study

  • 14.5 year mine life with 3.1 year payback
  • Improvement in grade, stripping ratio and operating cost
  • Significant increase in overall economics

SEPT 2010: Indicative Term Sheet for project finance debt from Itaύ BBA

  • Up to US$130 million

DEC 2010: Received preliminary environmental license (Licença Prévia), which confirms the understanding of the Environemntal Agency that the project is feasible from the environmental standpoint

MAR 2011: Received the construction license (Licença de Instalação)

Resource Estimates

In July 2010, the current Itafós Arraias SSP Project Mineral Resources were updated by Wardrop Consultants with a NI-43-101 compliant report. The resource estimated a deposit containing 58.8 million tonnes of measured and indicated mineral resources and 14.0 Mt of Inferred Resources. Current drilling has been focused in the Near Mine Area, which represents less than 20% of MBAC’s total land package.

In addition, inferred mineral resources totalling 23.9 million tonnes have been estimated for the Near Mine Project Area at a similar 2.8% P2O5 cut-off grade.

The Definite Feasibility Study (“DFS”) and Project Economics

MBAC has updated its mine plan for the Project based on the NI-43-101 compliant Updated Mineral Resource Estimate prepared by Wardrop for the Itafós Arraias SSP Project in Brazil which supported a positive DFS. With these increased resources the Company was able to optimize the current mine plan and reduce the pre-stripping volume to 4.7 Mt as well as reduce the stripping ratio, and increase the plant feed grade especially in the early years.

The Report supports an open pit mining operation, crushing, grinding and flotation concentration of the phosphate ore. The concentrate will be further reacted with sulphuric acid.

The Itafós Arraias SSP Project is estimated to produce on average 500,000 tonnes of SSP annually. The DFS details a total cost (including working capital) of approximately US$200 million (this amount includes $25 million in taxes, part of which is expected to be refunded, $20 million of expenditures in respect of pre-stripping and mining fleet and $16 million in contingencies).

The following is a summary of the key operating parameters and economics for the Project:

Mine Life 14.5 years
Average ROM grade 5.94% P2O5 in first 10 years (5.4% P2O5 over the mine life)
Strip Ratio 1.85 for the first 10 years (2.3 over the mine life)
Operating Cost (SSP) US$94.95 in first 4 years (US$104.32 per tonne over the mine life (granulated LOM))
Internal Rate of Return (IRR) 26.8%
Net Present Value @ 10% US$ 252.5 million
Payback 3.1 years after start-up
SSP Production Capacity to produce 1,750 tpd, approximately 500,000 t per annum
Concentrate Product 330,000 t per year of 28% P2O5 concentrate (used in SSP production)
94,000 t of 15% P2O5
Sulphuric Acid Capacity to produce 600 tpd, approximately 220,000 t per annum (used in SSP production)
10 MW of electricity production

The Report was prepared to an accuracy of ±10% for operating costs.